Transparency on Infrastructure Projects

A. Project title, location and detailed description; approved
budget for the contract; and winning contractor and the
detailed estimates of the bid awarded, within thirty
(30) calendar days from entering into the contract;

B. Start of construction, target of completion,
completion rate, project status and
the reason/s in case of delay;

C. Source of fund, implementing office responsible official, contract number and email address;
D. Detailed actual cost of the project, variations issued, if any, within thirty (30) calendar days from the
issuance of a certificate of completion
A. Project title, location and detailed description; approved budget for the contract; and winning contractor and the detailed estimates of the bid awarded, within thirty (30) calendar days from entering into the contract;B. Start of construction, target of completion, completion rate, project status and the reason/s in case of delay;C. Source of fund, implementing office responsible official, contract number and email address;D. Detailed actual cost of the project, variations issued, if any, within thirty (30) calendar days from the issuance of a certificate of completion
Project Title: Construction of Academic Building II (College of Dentistry) - Phase II - IB No. 2023-01 ABC: Php25,000,000.00 Winning Contractor: First Makeen Construction Contract Price: Php20,600,000.00Start Date: March 13, 2023 Target of Completion: January 22, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2023; Implementing Office: College of Dentistry/Infra/ CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-03-08 Email address: [email protected]Actual Cost: Variation Order: Php2,059,999.13
Project Title: Construction of Academic Building II - IB No. 2023-13 ABC: Php15,000,000.00 Winning Contractor: SCR Construction Contract Price: Php12,367,500.00Start Date: September 21, 2023 Target of Completion: April 18, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-09-38 Email address: [email protected]Actual Cost: Variation Order: Php1,236,750.00
Project Title: Repair of Roxas Hall Roofing - IB No. 2023-14 ABC: Php10,000,000.00 Winning Contractor: Urbancon Builders & Supply Contract Price: Php7,196,907.40Start Date: September 22, 2023 Target of Completion: May 15, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-09-40 Email address: [email protected]Actual Cost: Variation Order:Php 719,282.15
Project Title: Renovation of Administration Building Conference Hall (Teleconference Room) - IB No. 2023-19 ABC: Php2,600,000.00 Winning Contractor: First Makeen Construction Contract Price: Php1,965,250.00Start Date: September 07, 2023 Target of Completion: January 03, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: Php196,488.08
Project Title: Electrical Works for College of Dentistry Building (Proposed Substation and Feeder) - IB No. 2023-24 ABC: Php3,000,000.00 Winning Contractor: MDC Electrical Supplies and Services Contract Price: Php2,798,129.95Start Date: September 21, 2023 Target of Completion: February 03, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-37 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Renovation of Teacher's Center (Interior Works) - IB No. 2023-25 ABC: Php1,999,300.00 Winning Contractor: Urbancon Builders & Supply Contract Price: Php1,755,887.49Start Date: October 09, 2023 Target of Completion: January 07, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-09-41 Email address: [email protected]Actual Cost: Variation Order: if any
Establishment and/ or Support to the College of Medicine (Completion of Clinical Skills Laboratory of the College of Medicine) - IB No. 2023-37 ABC: Php40,000,000.00 Winning Contractor: Rock 101 Construction and Supply Contract Price: Php39,956,491.21Start Date: December 20, 2023 Target of Completion: August 16, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-12-73 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Construction of URGP/ Commercial Building - IB No. 2023-41 ABC: Php8,500,000.00 Winning Contractor: Ijojpa Construction Contract Price: Php6,960,721.59Start Date: December 20, 2023 Target of Completion: July 07, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-12-74 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Increase in Carrying Capacity of the College of Medicine - Phase II - IB No. 2023-46 ABC: Php30,000,000.00 Winning Contractor: ZTIM Construction and Supply Contract Price: Php22,274,451.75Start Date: January 10, 2024 Target of Completion: September 06, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-12-87 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Infrastructure and SMART Campus Development, Operationalization of Face to Face Classes and Upgrading/ Procurement of Equipment - IB No. 2023-58 ABC: Php8,415,000.00 Winning Contractor: Steven Construction and Supply Contract Price: Php6,364,975.33Start Date: January 10, 2024 Target of Completion: March 10, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2022 (Continuing Appropriations); Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-12-88 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Construction of WVSU Gymnasium (Phase I) ABC: Php50,000,000.00 Winning Contractor: F. Gurrea Construction Inc. Contract Price: Php48,985,573.39Start Date: June 25, 2021 Target of Completion: April 12, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2021; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2021-05-02 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Rehabilitation/ Repair of WVSU Grandstand ABC: Php999,892.69 Winning Contractor: SCR Construction Contract Price: Php999,000.00Start Date: January 09, 2024 Target of Completion: May 06, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number:JO No. 23-12-0101 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Increase in Carrying Capacity of the College of Medicine (COM Annex Building III - Phase I) - Re-bidding - IB No. 008-2021 ABC: Php46,000,000.00 Winning Contractor: Steven Construction and Supply Contract Price: Php45,719,242.88Start Date: January 10, 2022 Target of Completion: February 14, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2021; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: CA No. 12-07-2021 Email address: [email protected]Actual Cost: Variation Order:Php280,757.12
Project Title: Construction of Clinical Skills Laboratory WVSU College of Medicine - Phase I ABC: Php40,000,000.00 Winning Contractor: Steven Construction and Supply Contract Price: Php35,470,404.88Start Date: January 10, 2022 Target of Completion: September 01, 2023 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2021; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: CA No. 12-06-2021 Email address: [email protected]Actual Cost: Variation Order:Php3,546,316.04
Project Title: Repair of Roxas Hall Roofing - IB No. 2023-14 ABC: Php10,000,000.00 Winning Contractor: Urbancon Builders & Supply Contract Price: Php7,196,907.40Start Date: September 22, 2023 Target of Completion: March 20, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Renovation of Administration Building Conference Hall (Teleconference Room) - IB No. 2023-19 ABC: Php2,600,000.00 Winning Contractor: First Makeen Construction Contract Price: Php1,965,250.00Start Date: September 07, 2023 Target of Completion: December 16, 2023 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: PHP1,965,250.00 Variation Order: if any
Project Title: Electrical Works for College of Dentistry Building (Proposed Substation and Feeder) - IB No. 2023-24 ABC: Php3,000,000.00 Winning Contractor: MDC Electrical Supplies and Services Contract Price: Php2,798,129.95Start Date: September 21, 2023 Target of Completion: November 20, 2023 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Renovation of Teacher's Center (Interior Works) - IB No. 2023-25 ABC: Php1,999,300.00 Winning Contractor: Urbancon Builders & Supply Contract Price: Php1,755,887.49Start Date: October 09, 2023 Target of Completion: January 07, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Construction of URGP/ Commercial Building - IB No. 2023-41 ABC: Php8,500,000.00 Winning Contractor: Ijojpa Construction Contract Price: Php6,960,721.59Start Date: December 20, 2023 Target of Completion: July 07, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Increase in Carrying Capacity of the College of Medicine - Phase II - IB No. 2023-46 ABC: Php30,000,000.00 Winning Contractor: ZTIM Construction and Supply Contract Price: Php22,274,451.75Start Date: January 10, 2024 Target of Completion: September 06, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: if any
Project Title: Infrastructure and SMART Campus Development, Operationalization of Face to Face Classes and Upgrading/ Procurement of Equipment - IB No. 2023-58 ABC: Php8,415,000.00 Winning Contractor: Steven Construction and Supply Contract Price: Php6,364,975.33Start Date: January 10, 2024 Target of Completion: March 10, 2024 Completion Rate: Status and Reasons of delay: if anySource of Fund: GAA 2022 (Continuing Appropriations); Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: Variation Order: if any
Renovation of Administration Building Conference Hall (Teleconference Room) - IB No. 2023-19Start Date: September 07, 2023 Target of Completion: December 16, 2023 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2023; Implementing Office: CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2023-08-34 Email address: [email protected]Actual Cost: PHP1,965,250.00 Variation Order: if any
Construction and Rehabilitation/ Improvement of Buildings
Lot No. I (Construction of Storage Facilities)
IB No. 20-07-04
ABC: PhP1,600,000.00
Winning Contractor: Golden Heaven Builders and Construction Supply

Start Date: September 07, 2020;
Target of Completion: December 26, 2020;
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr. Reynaldo G. Germia
Actual Cost of the Project: PHP 1,469,272.41
Variation issued, if any: NA
Construction and Rehabilitation/ Improvement of Buildings
Lot No. III (Renovation of Nursing Skills Laboratory)
IB No. 20-07-04
ABC: PhP77,654.00
Winning Contractor: Golden Heaven Builders and Construction Supply
ConstructionStart Date: September 07, 2020;
Target of Completion: October 05, 2020
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020,
Implementing Office and Responsible Official: Campus Planning Office/Project Management Office (PMO) - Engr. Reynaldo G. Germia
Actual Cost of the Project: PHP 66,544.10
Variation issued, if any: NA
Construction and Rehabilitation/ Improvement of Buildings
Lot No. II (Repair of Wellness Center)
IB No. 20-07-04
ABC: PhP213,613.00
Winning Contractor: 3rd Dragon Builders Innovation
Start Date: September 07, 2020;
Target of Completion: October 22, 2020;
Completion Rate:Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr.Reynaldo G. Germia
Actual Cost of the Project: PHP 184,339.41
Variation issued, if any: NA
Construction of URGP/ Commercial Building (Re-bidding)
IB No. 20-08-11
ABC: PhP22,000,000.00
Winning Contractor: FLT Enterprises
Start Date: November 06, 2020;
Target of Completion: June 04, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr. Reysa Joy M. Batallones and Engr. Reynaldo G. Germia
Actual Cost of the Project: PHP 19,814,225.75
Variation issued, if any: ON-GOING Project
Various Civil Works
IB No. 20-10-13
Rehabilitation of Restrooms at COC
ABC: PhP600,000.00
Winning Contractor: IJOJPA Construction
Start Date: December 14, 2020;
Target of Completion: January 28, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez Engr. Reynaldo G. Germia
Actual Cost of the Project: PHP 508,984.28
Variation issued, if any:
Various Civil Works
IB No. 20-10-13
Construction of Restroom at Wellness Center
ABC: PhP670,000.00
Winning Contractor: IJOJPA Construction
Start Date: December 14, 2020;
Target of Completion: January 28, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez Engr. Reynaldo G. Germia
Actual Cost of the Project: PHP 568,518.89 Variation issued, if any: NA
Completion of GTBI building (4th Floor)
Proposed Roofing and Enclosure
IB No. 20-11-25
ABC: PhP3,600,000.00
Winning Contractor: Golden Heaven Builders and Construction Supply
Start Date: December 14, 2020;
Target of Completion: January 28, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez Engr.Reynaldo G. Germia
Actual Cost of the Project: 3,112,193.88
Variation issued, if any: ON-GOING Project
Rehabilitation of COM Annex Building (4th Floor)
IB No. 20-11-29
ABC: PhP3,386,000.00
Winning Contractor: Sky Builders Construction and Supply
Start Date: January 11, 2021
Target of Completion: April 21, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 2,508,238.79
Variation issued, if any: ON-GOING Project
Replacement of Gutters at Roxas Hall Building
IB No. 21-05-15
ABC: PhP504,000.00
Winning Contractor: Sky Builders Construction and Supply
Start Date: July 09, 2021
Target of Completion: August 23, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 444,334.80
Variation issued, if any: ON-GOING Project
Replacement of Gutters at Roxas Hall Building
IB No. 21-05-15
ABC: PhP504,000.00
Winning Contractor: Sky Builders Construction and Supply
Start Date: July 09, 2021
Target of Completion: August 23, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official:
Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 444,334.80
Variation issued, if any: ON-GOING Project
Construction of Generator Power House
IB No. 21-08-23
ABC: PhP530,000.00
Winning Contractor: Urbancon Builders & Supply
Start Date:September 27, 2021
Target of Completion: November 26, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 468,888.88
Variation issued, if any: ON-GOING Project
Construction of Generator Power House
IB No. 21-08-23
ABC: PhP530,000.00
Winning Contractor: Urbancon Builders & Supply
Start Date:September 27, 2021
Target of Completion: November 26, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 468,888.88
Variation issued, if any: ON-GOING Project
Renovation of Administration and Records Building
IB No. 21-09-26
ABC: PhP729,125.00
Winning Contractor: Sky Builders and Construction Supply
Start Date:November 02, 2021
Target of Completion: December 17, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 578,837.52
Variation issued, if any: ON-GOING Project
Construction of Academic Building II (College of Dental Medicine)
RFQ No. 21-04-028
ABC: PhP52,534,000.00
Winning Contractor: G. Uy Construction
Start Date: June 21, 2021
Target of Completion: Februrary 16, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: GAA 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 50,925,688.45
Variation issued, if any: ON-GOING Project
Construction of WVSU Gymnasium - Phase I
RFQ No. 21-03-024
ABC: PhP50,000,000.00
Winning Contractor: F. Gurrea Construction Inc.
Start Date: June 25, 2021
Target of Completion: April 21, 2022
Completion Rate:Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 48,985,573.39
Variation issued, if any: ON-GOING Project
Various Civil Works
IB No. 21-10-34
ABC: PhP4,450,000.00 - Lot I - Expansion of Admin Building (Left Wing)
Winning Contractor: 3rd Dragon Builders Innovation
Start Date: December 01, 2021
Target of Completion: June 02, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 3,646,182.88
Variation issued, if any: ON-GOING Project
Various Civil Works
IB No. 21-10-34
ABC: PhP3,262,000.00 - Lot II - Renovation of Administration Building Restrooms
Winning Contractor: Urbancon Builders & Supply
Start Date: December 06, 202
Target of Completion: March 06, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2022
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 2,528,886.45
Variation issued, if any: ON-GOING Project
Construction and Rehabilitation/ Improvement of Buildings
Lot No. I (Construction of Storage Facilities)
IB No. 20-07-04
ABC: PhP1,600,000.00
Winning Contractor: Golden Heaven Builders and Construction Supply
Start Date: September 07, 2020;
Target of Completion: December 26, 2020
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr. Reynaldo G. Germia
Actual Cost of the Project: PhP 1,469,272.41
Variation issued, if any: NA
Construction and Rehabilitation/ Improvement of Buildings
Lot No. III (Renovation of Nursing Skills Laboratory)
IB No. 20-07-04
ABC: PhP77,654.00
Winning Contractor: Golden Heaven Builders and Construction Supply
Start Date: September 07, 2020;
Target of Completion: October 05, 2020
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2022
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr. Reynaldo G. Germia
Actual Cost of the Project: PhP 66,544.10
Variation issued, if any: NA
Construction and Rehabilitation/ Improvement of Buildings
Lot No. II (Repair of Wellness Center)
IB No. 20-07-04
ABC: PhP213,613.00
Winning Contractor: 3rd Dragon Builders Innovation
Start Date: September 07, 2020;
Target of Completion: October 22, 2020
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr. Reynaldo G. Germia
Actual Cost of the Project: PhP 184,339.41
Variation issued, if any: NA
Construction of URGP/ Commercial Building (Re-bidding)
IB No. 20-08-11
ABC: PhP22,000,000.00
Winning Contractor: FLT Enterprises
Start Date: November 06, 2020;
Target of Completion: June 04, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Engr. Reysa Joy M. Batallones and Engr. Reynaldo G. Germia
Actual Cost of the Project: 19,814,225.75
Variation issued, if any: ON-GOING Project
Various Civil Works - Rehabilitation of Restrooms at COC
IB No. 20-10-13
ABC: PhP600,000.00
Winning Contractor: IJOJPA Construction
Start Date: December 14, 2020;
Target of Completion: January 28, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez Engr. Reynaldo G. Germia
Actual Cost of the Project: 508,984.28
Variation issued, if any:
Various Civil Works - Construction of Restroom at Wellness Center
IB No. 20-10-13
ABC: PhP670,000.00
Winning Contractor: IJOJPA Construction
Start Date: December 14, 2020;
Target of Completion: January 28, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez Engr. Reynaldo G. Germia
Actual Cost of the Project: 568,518.89
Variation issued, if any: NA
Completion of GTBI building (4th Floor) - Proposed Roofing and Enclosure
IB No. 20-11-25
ABC: PhP3,600,000.00
Winning Contractor: Golden Heaven Builders and Construction Supply
Start Date: December 14, 2020;
Target of Completion: January 28, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez Engr. Reynaldo G. Germia
Actual Cost of the Project: 3,112,193.88
Variation issued, if any: ON-GOING Project
Rehabilitation of COM Annex Building (4th Floor)
IB No. 20-11-29
ABC: PhP3,386,000.00
Winning Contractor: Sky Builders Construction and Supply
Start Date: January 11, 2021
Target of Completion: April 21, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2020
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 2,508,238.79
Variation issued, if any: ON-GOING Project
Replacement of Gutters at Roxas Hall Building
IB No. 21-05-15
ABC: PhP504,000.00
Winning Contractor: Sky Builders Construction and Supply
Start Date: July 09, 2021
Target of Completion: August 23, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 444,334.80
Variation issued, if any: ON-GOING Project
Construction of Generator Power House
IB No. 21-08-23
ABC: PhP530,000.00
Winning Contractor: Urbancon Builders & Supply
Start Date:September 27, 2021
Target of Completion: November 26, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 468,888.88
Variation issued, if any: ON-GOING Project
Renovation of Administration and Records Building
IB No. 21-09-26
ABC: PhP729,125.00
Winning Contractor: Sky Builders and Construction Supply
Start Date:November 02, 2021
Target of Completion: December 17, 2021
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 578,837.52
Variation issued, if any: ON-GOING Project
Construction of Academic Building II (College of Dental Medicine)
RFQ No. 21-04-028
ABC: PhP52,534,000.00
Winning Contractor: G. Uy Construction
Start Date: June 21, 2021
Target of Completion: Februrary 16, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: GAA 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 50,925,688.45
Variation issued, if any: ON-GOING Project
Construction of WVSU Gymnasium - Phase I
RFQ No. 21-03-024
ABC: PhP50,000,000.00
Winning Contractor: F. Gurrea Construction Inc.
Start Date: June 25, 2021
Target of Completion: April 21, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 48,985,573.39
Variation issued, if any: ON-GOING Project
Various Civil Works -
IB No. 21-10-34
ABC: PhP4,450,000.00 - Lot I - Expansion of Admin Building (Left Wing)
Winning Contractor: 3rd Dragon Builders Innovation
Start Date: December 01, 2021
Target of Completion: June 02, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 3,646,182.88
Variation issued, if any: ON-GOING Project
Various Civil Works
IB No. 21-10-34
ABC: PhP3,262,000.00 - Lot II - Renovation of Administration Building Restrooms
Winning Contractor: Urbancon Builders & Supply
Start Date: December 06, 2021
Target of Completion: March 06, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 2,528,886.45
Variation issued, if any: ON-GOING Project
Rehabilitation of Road
IB No. 21-10-37
ABC: PhP4,500,000.00
Winning Contractor: Sky Builders Construction and Supply
Start Date: December 17, 2021
Target of Completion: April 16, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 4,069,501.01
Variation issued, if any: ON-GOING Project
Construction of GTBI Building Concrete Fire Escape Staircase
IB No. 21-11-42
ABC: PhP1,530,000.00
Winning Contractor: 3rd Dragon Builders Innovation
Start Date: January 05, 2022
Target of Completion: May 05, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: Special Trust Fund 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 1,390,794.51
Variation issued, if any: ON-GOING Project
Construction of Clinical Skills Laboratory WVSU College of Medicine - Phase I
IB No. 007-2021
ABC: PhP40,000,000.00
Winning Contractor: Steven Construction and Supply
Start Date: January 10, 2022
Target of Completion: September 07, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: GAA 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 35,470,404.88
Variation issued, if any: ON-GOING Project
Increase in Carrying Capacity of the College of Medicine
(COM Annex Building III - Phase I - Re-bidding) - Phase I
IB No. 008-2021
ABC: PhP46,000,000.00
Winning Contractor: Steven Construction and Supply
Start Date: January 10, 2022
Target of Completion: September 07, 2022
Completion Rate: Project status and the reason/s in case of delay:
Source of Fund: GAA 2021,
Implementing Office and Responsible Official: Campus Planning Office
Project Management Office (PMO) - Architect Gerad L. Ibañez
Actual Cost of the Project: 45,719,242.88
Variation issued, if any: ON-GOING Project
Various Civil Works
Lot I - Repair of Various Main Campus Buildings
(Ceiling Eaves & G.I. Gutters) and
Lot II - Construction of Generator House Extension
Start Date: June 06, 2022 (Lot I)
Target of Completion: August 05, 2022 (Lot I)
Start Date: June 06, 2022 (Lot II)
Target of Completion: July 01, 2022 (Lot II)
Completion Rate: Status and Reasons of delay: if any
Source of Fund: Special Trust Fund 2022 (Lot I and II);
Implementing Office: Infra/ CPPO/ Ar. Gerard L. Ibañez;
Contract Number: 2022-05-17
Email address: [email protected]
Actual Cost: Lot I - 1,487,557.89 and Lot II - 209,163.61
Variation Order: if any
Additional Works for Expansion of Administration Building (Left Wing)
Start Date: August 31, 2022 Target of Completion: December 09, 2022 Completion Rate: Status and Reasons of delay: if any
Source of Fund: Special Trust Fund 2022; Implementing Office: Infra/ CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2022-08-35 Email address: [email protected]
Actual Cost: 1,007,608.04 Variation Order: if any
Construction of URGP Building - Phase IIStart Date: October 14, 2022 Target of Completion: March 13, 2023 Completion Rate: Status and Reasons of delay: if anySource of Fund: Special Trust Fund 2022;
Implementing Office: URGP/Infra/ CPPO/ Ar. Gerard L. Ibañez;
Contract Number: 2022-10-44 Email address: [email protected]
Actual Cost: PHP6,903,523.21 Variation Order: if any
Construction of Academic Building II (College of Dentistry) - Phase II - IB No. 2023-01
Start Date: March 13, 2023 Target of Completion: November 08, 2023 Completion Rate: Status and Reasons of delay: if any
Source of Fund: GAA 2023; Implementing Office: College of Dentistry/Infra/ CPPO/ Ar. Gerard L. Ibañez; Contract Number: 2022-10-44 Email address: [email protected]
Actual Cost: PHP20,600,000.00 Variation Order: if any